The primary sources of law in the Kingdom of Saudi Arabia that govern construction contracts are:
According to Articles 463-467 of The Civil Transactions Law contains several obligations of the contractor in the contract, as follows:
According to Article 469 of the Civil Transactions Law, a contractor is entitled to their wages once they have completed the agreed-upon work and handed it over to the employer. If the work consists of multiple parts, the employer is obligated to pay the contractor's wages in proportion to the amount of work completed, after it has been inspected and accepted by the employer.
Regarding claims for an increase in wages due to increased material costs, a contractor is not entitled to make such a claim unless one of the following two conditions is met: (1) the error in material prices was caused by the employer, or (2) the contractor and employer had previously agreed to an increase in wages according to Article 471 of the Civil Transactions Law.
In Saudi Arabia, there are two common types of contracts in construction projects:
Lump Sum Contract is when the contractor agrees to perform the work for a fixed price, which includes all costs, profits, and risks. The contractor is responsible for planning, designing, and executing the project, and is only paid the agreed-upon lump sum, regardless of the actual cost and bears the risk of cost overruns or changes in project scope.
Cost-Plus Contract is when the contractor is paid for all expenses incurred during the project, including labor, materials, equipment, and overheads. The contractor is also entitled to a profit margin (usually a percentage of the total cost). The client is responsible for paying the contractor's actual costs plus the agreed-upon profit margin and bears less risk than in a lump sum contract, as they are reimbursed for actual costs.
Key differences between Lump Sum and Cost-Plus Contracts:
Cost-Plus | Lump Sum |
| |
based on actual costs plus profit. | fixed price. | Price | 1 |
more flexibility in their expenses. | bear more risk due to potential cost overruns or changes in project scope. | Risk | 2 |
contracts allow for more involvement in decision-making. | Clients have less control over Lump Sum contractors' actions and expenses. | Control | 3 |
contracts are suitable for projects with changing or uncertain scope. | contracts are often used for well-defined projects. | Scope | 4 |
According to The Saudi government Tenders and Procurement Law Article 74:
"Contracts may be extended and fines may be waived in the following cases:
In Saudi Arabia, Article 107 of the Civil Transactions Law states that "If a contracting party in a bilateral contract fails to perform his obligation, the other contracting party may, after notifying the breaching party, demand implementation or termination of the contract, and may claim compensation in either case, if applicable. The court may dismiss the petition for termination if the unperformed part is insignificant compared to the obligation. " Similarly, Article 114 states that "If, in bilateral contracts, the corresponding obligations are due, a contracting party may refuse to perform his obligations if the other contracting party fails to perform his corresponding obligation. "
Contractors in Saudi Arabia typically include provisions in their contracts that address non-payment by employers, including specific clauses on payment terms, late payment penalties, and interest rates.
The typical processes and procedures that contractors follow when there are changes or modifications to the initial scope of work during a construction project are as follows:
According to Saudi Civil Transactions Law, the standard protocols and best practices that construction contractors in Saudi Arabia follow to identify, document, and resolve any defects or deficiencies that arise during the execution of a project are as follows:
In cases where defects or deficiencies are found, the contractor may be liable for rectification costs, depending on the circumstances. If the defects or deficiencies are not attributable to the contractor, they may not be liable for rectification costs.
Additionally, contractors in Saudi Arabia are expected to comply with Article 467 of the Saudi Civil Transactions Law, which states that if a thing is destroyed or damaged prior to delivery due to a reason not attributable to the contractor, they may not demand payment of the agreed-upon fee or reimbursement of expenses incurred.
Contractors should also be aware of the Saudi Civil Transactions Law:
Article 477
If the contractor commences execution of the work but fails to complete it for a reason not attributable to him, he shall be paid for the completed work and for any expenses he incurs for the uncompleted work to the extent of the benefit accrued to the client.
Article 467
Article 466
Based on article 55 from Law of Evidence " Proof by digital evidence shall have the same legal effect as proof by writing as set out in this Law".
The execution of a construction contract can be done remotely, but it requires specific procedures and documentation to ensure the validity and enforceability of the contract. Here are the steps to execute a construction contract remotely in Saudi Arabia:
It is essential to note that remote execution of a construction contract in Saudi Arabia may require additional documentation and procedures compared to traditional methods. It is recommended to consult with legal experts and industry professionals to ensure compliance with Saudi laws and regulations.
Some benefits of remote execution of construction contracts in Saudi Arabia include:
However, it is crucial to ensure that all parties involved understand the remote execution process and agree on the terms and conditions before executing the contract remotely.
Construction contracts can be executed in a foreign currency, but there are certain requirements and considerations to be aware of.
Contractors who wish to continue work on official holidays must provide compensation to their workers in accordance with the Saudi Labor Law, Article 107. This article specifies the following conditions:
A construction contract can be terminated due to changes in the project's scope under certain circumstances. Here are some possible scenarios:
Before terminating a construction contract in Saudi Arabia due to changes in scope or other reasons, it is essential for both parties to:
In addition to these steps, contractors should also:
It is crucial for contractors to understand Saudi Arabian laws and regulations regarding construction contracts, including termination clauses and dispute resolution mechanisms. Consulting with legal experts can help ensure that contractors navigate these complexities effectively and protect their interests in case of termination.
If the contract does not include specific terms or a specific period for completion, Article 465 states that "the contractor shall complete the work in accordance with the terms of the contract and within the agreed-upon period. If the contract does not include specific terms or a specific period for completion, the contractor shall complete the work in accordance with the prevailing standards and within a reasonable period as required by the nature of the work."
According to the Civil Transaction Law in Saudi Arabia (Article 467), the contractor's entitlement to claim wages and expenses for a damaged or destroyed item depends on the circumstances.
Scenario 1: Item destroyed or damaged before delivery to the employer, due to a reason not attributable to the contractor
In this case, the contractor is not entitled to demand payment of the agreed-upon fee or reimbursement of expenses incurred for the item, unless the employer was in breach of their obligation to take delivery of the work at the time of destruction or damage. This means that if the employer was supposed to accept the item, but failed to do so, the contractor can still claim payment for the item.
Scenario 2: Item provided by the employer, destroyed or damaged before delivery, due to a reason not attributable to the contractor
In this case, the employer cannot demand payment from the contractor for the value of the materials, unless:
This means that if the employer provided materials and they were destroyed or damaged before delivery, and the contractor was not notified of their breach of obligation, and it is clear that the damage would have occurred regardless of whether the contractor delivered the work or not, then the employer cannot claim reimbursement from the contractor.
In summary:
It is essential for contractors and employers in Saudi Arabia to understand these provisions and negotiate contract terms accordingly to ensure clarity and minimize potential disputes.
According to the Implementing Regulation of Saudi Building Code (Article 22). " The license holder or his representative shall notify the inspector when the work is ready for inspection according to the construction stages, and shall provide all the documents, drawings and the necessary supplies for the required inspection and testing works." the license holder or their representative is responsible for notifying the building inspector to conduct the required inspections and tests. This means that it is the contractor's responsibility to notify the inspector when the work is ready for inspection, at each stage of construction, and provide all necessary documents, drawings, and information required for the inspections and tests.
In a construction project in Saudi Arabia, the license holder (usually the contractor) or their representative (e.g., a project manager or engineer) is responsible for coordinating with the building inspector to ensure that all necessary inspections and tests are conducted throughout the construction process. This includes inspections at various stages of construction, such as:
By notifying the building inspector and providing all required documentation, the license holder ensures that the inspector can conduct thorough inspections and tests to verify that the work meets the requirements of the Saudi Building Code and other relevant regulations.
It is essential for contractors and project stakeholders in Saudi Arabia to understand their responsibilities regarding inspections and testing to ensure compliance with regulatory requirements and to maintain a safe and quality-built construction project.
According to the Saudi Building Code application law (Article 29), in a construction project in Saudi Arabia, the designer supervising the implementation of the building and the executor (contractor)are jointly responsible for compensating the owner if there is a complete or partial demolition of the existing buildings.
This joint responsibility applies to:
This means that both the designer and contractor are liable for any damage or loss caused by defects in their work, even if the defect or demolition resulted from a fault in the land itself or the employer's consent to erect defective buildings and facilities.
In addition, if the designer's work is limited to developing the design only, without supervising implementation, they will still be responsible for design defects.
The article also states that any condition intended to exempt the contractor or supervising designer from this warranty or limit it shall be invalid. This means that contractors and designers cannot include clauses in their contracts that attempt to limit or exclude their liability for defects or damages.
In summary, in a construction project in Saudi Arabia, both the designer and contractor are jointly responsible for compensating the owner if there is a complete or partial demolition of existing buildings due to defects in their work.
According to the Civil Transaction Law Article 468 in Saudi Arabia, if a contractor completes their work and makes it available to the employer, the employer is obligated to take possession of the completed work. If the employer fails to take delivery of the work without a legitimate reason, and the work is destroyed or damaged while in the contractor's possession for reasons not attributable to the contractor's transgression or negligence, the contractor is not obligated to compensate the employer.
This means that if the contractor has completed their work and made it available to the employer, but the employer does not take possession of it, and something happens to the work (e.g., damage or destruction), the contractor is not liable for compensation. The contractor is not responsible for any losses or damages caused by the employer's failure to take possession of the completed work.
In other words, if the employer fails to fulfill their obligation to accept delivery of the completed work, they cannot claim compensation from the contractor for any subsequent losses or damages that may occur.
It's essential for contractors and employers in Saudi Arabia to understand their responsibilities and obligations under this article, as it can have significant implications for their rights and liabilities in case of disputes or issues related to project delivery.
According to the Civil Transaction Law Article 474 in Saudi Arabia, a subcontractor is not permitted to directly demand or claim anything from the employer (client) if that something is something the main contractor is entitled to under the contract. In other words, a subcontractor cannot bypass the main contractor and demand payment or compensation directly from the employer. Instead, they must go through the main contractor to make any claims or demands.
A subcontractor may only demand payment or compensation from the employer if they are referred to do so by the main contractor. This is to maintain the contractual hierarchy and ensure that payments and compensation are made through the correct channels. It also helps to prevent disputes and confusion between the subcontractor and the employer.
According to the Saudi Civil Transaction Law Articles 475-478, a construction contract may expire or come to an end under the following circumstances or conditions:
Article 475: A contract for service shall terminate upon completion of the agreed-upon work.
Article 476: Either contracting party may demand termination of the contract for service in the event of an exigent matter that affects his obligation in the performance of the contract in such case, the terminating party shall compensate the other party for any harm sustained.
Article 477: If the contractor commences execution of the work but fails to complete it for a reason not attributable to him, he shall be paid for the completed work and for any expenses he incurs for the uncompleted work to the extent of the benefit accrued to the client.
Article 478: A contract for service shall terminate under the following conditions:
These articles outline specific circumstances that can lead to a construction contract terminating, including completion of work, exigent matters affecting performance, failure to complete work, and contractor's death.